Microsoft Project 2007 set current date when create new task



Start new tasks on the current date
Show AllShow All

Microsoft Office Project 2007 starts new tasks on the project start date by default.
You can, however, specify that new tasks start on the current date instead of the project start date.

1. On the Tools menu -> click Options -> and then click the Schedule tab.


2. In the Scheduling Options for 'project name'
3. set New Task to = 'Start on Current Date'